The appearance of the Saigon One Tower building over 11 years

Booking.com

HO CHI MINH CITY – Saigon One Tower (District 1), after 11 years of being abandoned, now has a new look, but the investor can only cover the outside glass, other items cannot be made.

Click to flip the photo

Click to flip the photo

Located on a land of more than 6,600 m2 of golden land at the corner of Ham Nghi – Ton Duc Thang – Vo Van Kiet streets (District 1), Saigon One Tower (formerly known as Saigon M&C Tower) is a project with a prime location in Ho Chi Minh City.

Construction started in 2009, with a total capital of more than VND 5,000 billion, the third highest in Ho Chi Minh City with over 185 m including 42 floors and 5 basements, planned as a high-rise commercial building including offices and shared apartments. apartments, serviced apartments and commercial centers. After building about 80% of the rough, the project stopped construction in 2011, since then the decade has been abandoned, seized to settle debts…

From August, the construction site has been busy constructing glass panels on floors and decorating the exterior of the building. The image seen from above on the afternoon of August 30, the building is basically finished with glass panels, bright in one corner, in contrast to the abandoned scene 4 years ago.

Click to flip the photo

Click to flip the photo

One side of a 42-storey building seen from the corner of Ton Duc Thang street – Ham Nghi at present compared to 2017.

According to the Ho Chi Minh City Department of Construction, this work has been stopped for more than 11 years, leading to the possibility that the bearing glass frames cause unsafety as well as affect the urban beauty. Therefore, the city allows investors to install new glass frames to decorate the city, ensure the safety of people and must be completed before September 1. For other items, the investor cannot do it because this project is currently waiting for the conclusion of the Government Inspector.

Click to flip the photo

Click to flip the photo

View from below of the building with a new barrier with the same name of another investor and a new look compared to 2015.

The roof of the building in 2015 was not covered with glass, covered with dust, some safety nets were blown off, and the inside was bare concrete floors and columns.

In 2015, many items inside after nearly 4 years of stopping construction became disheveled, covered with dust. The glass panels on the lower floors are old and dusty outside.

Click to flip the photo

Click to flip the photo

Saigon One Tower and “brother” Bitexco now and 7 years ago.

On the morning of August 30, one day before the end of construction, many workers continued to cover the glass, clean on the high floors and decorate the exterior of the building.

Click to flip the photo

Click to flip the photo

Saigon One Tower building seen from across the Saigon River at night time compared to 6 years ago.

The first investor of Saigon One Tower was Saigon M&C Real Estate Joint Stock Company (later renamed Saigon One Tower Joint Stock Company). In 2018, the building was announced by the Vietnam Asset Management Company (VAMC) to be auctioned to handle bad debts of more than VND 7,000 billion….

The new perspective of the building after changing to a new owner is Viva Land Company.

Viva Land Company was established in May 2019, chartered capital of 2,000 billion VND, the main business is real estate business. After changing owners, Saigon One Tower also had a new name, IFC One Saigon.